MULTAN: Javed Akhtar, Commissioner Multan division on Wednesday assessed the ongoing development projects under Community Development Programme (CDP).
According to the details, the commissioner assessed the progress of 585 projects under Phase-II, and Phase-III of CDP.
Speaking on the occasion the commissioner directed the relevant authorities to finish the work on Phase-II by June 10.
The officials told the commissioner that out of 239 schemes under phase-II, work on 160 schemes has been finished while the development work on the remaining schemes is underway.
Further, the officials added that 346 development projects under Phase-III will be initiated in the upcoming days at the cost of Rs3.2bn.
For news and blogs, visit Graana.com
Islamabad: The federal government is likely to include the Tax Laws (Amendment) Bill, 2024 in…
Islamabad: The International Monetary Fund (IMF) Executive Board is set to convene on Friday, May…
Members of the National and Punjab Assemblies have lauded the provincial government’s plan to introduce…
ISLAMABAD: The Capital Development Authority (CDA) has recorded a historic development expenditure of Rs25 billion…
ISLAMABAD: The federal government is set to inaugurate the Islamabad Information Technology Park on August…
Lahore, April 23, 2025 – The city of Lahore has successfully completed the construction of…