ISLAMABAD: The Islamabad Expressway projects, including PDW Underpass and Korang Bridge, will be concluded by the deadlines set for June 30 and December 31, the Capital Development Authority (CDA) ensured.
Since October, work on 40 out of 68 piles have been completed, whereas 16 out of 33 girders accomplished under the Korang Bridge project worth Rs650 million.
The authorities have also completed 70 per cent of work on the retaining walls.
The asphalt work is in progress on the east side ramps of the PWD Underpass, where the traffic will be diverted upon completion. The authorities have also completed shifting of utility services like IESCO and SNGPL.
The signal-free and U-turns-free road till project aimed at averting traffic jams will smooth out the flow for the daily commuters and residents living in housing societies along Islamabad Expressway and other adjoining areas.
For news and blogs, visit Graana.com.
Islamabad: The chairman of the Capital Development Authority (CDA) and Chief Commissioner Islamabad, Muhammad Ali…
Peshawar: The Khyber Pakhtunkhwa government is exploring plans to construct a 31-kilometre outer ring road…
Islamabad: The National Highway Authority (NHA) has spent more than half of its development budget…
Karachi: A high-level meeting chaired by Sindh Minister for Local Government Syed Nasir Hussain Shah…
Riyadh: Saudi Real Estate Co. (Al Akaria) has signed a long-term lease agreement with Amsa…
Rawalpindi: The divisional administration has begun acquiring land for the Rs5 billion Thalian Interchange, a…