ISLAMABAD: The Islamabad Expressway projects, including PDW Underpass and Korang Bridge, will be concluded by the deadlines set for June 30 and December 31, the Capital Development Authority (CDA) ensured.
Since October, work on 40 out of 68 piles have been completed, whereas 16 out of 33 girders accomplished under the Korang Bridge project worth Rs650 million.
The authorities have also completed 70 per cent of work on the retaining walls.
The asphalt work is in progress on the east side ramps of the PWD Underpass, where the traffic will be diverted upon completion. The authorities have also completed shifting of utility services like IESCO and SNGPL.
The signal-free and U-turns-free road till project aimed at averting traffic jams will smooth out the flow for the daily commuters and residents living in housing societies along Islamabad Expressway and other adjoining areas.
For news and blogs, visit Graana.com.
Islamabad: The Federal Board of Revenue has updated property valuation rates across 68 locations in…
Dubai’s residential real estate market maintained its upward momentum in November 2025, with the latest…
Saudi Arabia’s Real Estate General Authority (REGA) has announced the launch of a new platform…
Dubai: Tomorrow World Group, a global enterprise with a 20-year presence in the emirate, has…
Islamabad: The Capital Development Authority has begun a citywide rehabilitation and upgrading campaign, starting…
Dubai: The emirate’s real estate sector continued its strong performance in November 2025, posting transactions…