CDA ensures timely completion of Islamabad Expressway projects

ISLAMABAD: The Islamabad Expressway projects, including PDW Underpass and Korang Bridge, will be concluded by the deadlines set for June 30 and December 31, the Capital Development Authority (CDA) ensured.

invest with imarat

Islamabad’s emerging city centre

Learn More

Since October, work on 40 out of 68 piles have been completed, whereas 16 out of 33 girders accomplished under the Korang Bridge project worth Rs650 million.

The authorities have also completed 70 per cent of work on the retaining walls.

The asphalt work is in progress on the east side ramps of the PWD Underpass, where the traffic will be diverted upon completion. The authorities have also completed shifting of utility services like IESCO and SNGPL.

The signal-free and U-turns-free road till project aimed at averting traffic jams will smooth out the flow for the daily commuters and residents living in housing societies along Islamabad Expressway and other adjoining areas.

 

For news and blogs, visit Graana.com.

Maham Tahir

Recent Posts

Exploring the District of Matiari

Matiari, a district in Sindh province rich in history and culture, is well-known for its…

14 hours ago

Journey Along the Indus Highway: Exploring Pakistan’s Lifeline

The Indus Highway, officially called National Highway 55 (N-55), is a 1264 km two—to four-lane…

16 hours ago

Exploring Kairpur Tamewali

Khairpur Tamewali is a town located in Bahawalpur, Pakistan. Known initially as Tanori, named after…

18 hours ago

Batkhela: A Hidden Treasure In Malakand Valley

Amidst the lush valleys of the Malakand region in Khyber Pakhtunkhwa, Pakistan, lies the city…

2 days ago

All You Need to Know About Ilyasi Masjid

Situated at the base of a hill with natural springs and shaded by a verdant…

2 days ago

A Guide to Phool Nagar

Phool Nagar is in Pakistan's Punjab Province, in the Kasur District. It changed its name…

2 days ago