Chairman CDA Reviews Progress on Margalla Road and Jinnah Convention Centre Renovations

Islamabad – CDA Chairman Muhammad Ali Randhawa visited the construction and widening project of the Margalla Road (Bari Imam portion) early Monday morning to review the ongoing work. The relevant officers also accompanied him during the visit.
During the briefing, the Chairman was briefed that the relocation of IESCO’s power lines at the site is underway. He was further informed that the ongoing heavy spells of monsoon rains had affected the pace of the work.

invest with imarat

Islamabad’s emerging city centre

Learn More

Despite this, about 70% of the project’s base work on the southern carriageway has been completed, while 1 kilometre of base work on the northern carriageway has also been finished. CDA Chairman mentioned that the construction of this portion of Margalla Avenue would significantly improve traffic flow in the city.

It is worth noting that Federal Interior Minister Mohsin Naqvi had earlier instructed that work on this long-delayed project, pending for 17 years, should be resumed. The current work on the construction and widening of Margalla Road, which had been stalled since 2008, has been restarted and will be completed as soon as possible, according to the instructions of Federal Interior Minister Mohsin Naqvi.

Later on, the chairman also visited the Jinnah Convention Centre. On this occasion, he was briefed about the ongoing renovation and refurbishment work at the Jinnah Convention Centre. CDA Chairman Muhammad Ali Randhawa emphasized that the pace of the renovation work at the Convention Centre should be accelerated and that international standards should be maintained during the refurbishment of the Jinnah Convention Centre.

Arslan Siddiqui

Recent Posts

CDA Directs Fast-Track Handover of Developed Plots in Islamabad Sectors

Islamabad: The chairman of the Capital Development Authority (CDA) and Chief Commissioner Islamabad, Muhammad Ali…

14 hours ago

KP Government Considers 31km Outer Ring Road in Peshawar to Ease Traffic

Peshawar: The Khyber Pakhtunkhwa government is exploring plans to construct a 31-kilometre outer ring road…

5 days ago

NHA Utilises 56% of Development Budget in First Half of FY26

Islamabad: The National Highway Authority (NHA) has spent more than half of its development budget…

7 days ago

Karachi to Upgrade 183 Roads Under Special Infrastructure Program

Karachi: A high-level meeting chaired by Sindh Minister for Local Government Syed Nasir Hussain Shah…

2 weeks ago

Al Akaria Signs SR1.2 Billion Lease Deal for Amsa Vue Residential Compound in Riyadh

Riyadh: Saudi Real Estate Co. (Al Akaria) has signed a long-term lease agreement with Amsa…

2 weeks ago

Land Acquisition Begins for Thalian Interchange of Rawalpindi Ring Road Project

Rawalpindi: The divisional administration has begun acquiring land for the Rs5 billion Thalian Interchange, a…

2 weeks ago