ISLAMABAD: Construction work on the long-awaited underpass connecting sectors G-7 and G-8 has been initiated as excavators began digging the eastern side of Faisal Avenue.
The project worth Rs395 million was approved by the Capital Development Authority (CDA) last year and has been scheduled for completion within six months.
The civic authority has also procured a tree transplant device for the safe relocation of fully grown pine cheer trees lined alongside Faisal Avenue to protect them from destruction. Additionally, about 100 trees of the same species have been planted near the underpass to preserve the green identity of the area.
To avoid traffic disruption due to the construction work, a comprehensive traffic diversion plan has been drawn up. It is being implemented by the police and CDA’s Transport & Traffic Planning Directorate.
CDA had originally approved the construction of the underpass in 2014 as part of Islamabad’s Master Plan, which recommends building underpasses to link the sectors of the city.
For more news and blogs, visit Graana.com.
The federal government has announced the abolition of Right of Way (RoW) charges on federal…
Federal Minister for Railways Hanif Abbasi announced that several major projects — including the digitalization,…
Islamabad, Aug 7: A delegation of Islamabad's parliamentarians met with CDA Chairman and Chief Commissioner…
Islamabad – The National Highway Authority (NHA) has announced an ambitious upgrade of the Karachi…
Islamabad: The National Highway Authority (NHA) is moving forward with plans to build a tunnel…
Islamabad: Pakistan’s cement industry kicked off the fiscal year 2025–26 on a strong note, recording…