ISLAMABAD: In a bid to relieve the issue of traffic congestion on Islamabad Expressway, the Capital Development Authority (CDA) has fast-tracked the expansion work of Islamabad Expressway.
According to the details, the expansion of the Koral to Rawat portion is being widened on a priority basis while the PWD underpass has already been completed.
Similarly, the Korang to Soan part of the expressway is developed by FWO at a cost of Rs2.23bn which includes 1.93km of roads and service roads.
The last phase of the project includes the expansion of Soan Bridge which will be initiated in June under PSDP.
For news and blogs, visit Graana.com.
Lahore: In a landmark development, the Punjab Environment Department has issued its first-ever comprehensive environmental…
Islamabad, Oct 13: The Islamabad district administration has clarified that all roads in the federal…
Islamabad: Capital Development Authority (CDA) and the Overseas Pakistanis Foundation (OPF) have agreed to collaborate on…
Rawalpindi: The Rawalpindi Municipal Corporation (RMC) has finalized a phased plan to complete multiple ongoing…
Islamabad: Federal Minister for Communications Abdul Aleem Khan has unveiled a wide-ranging reform strategy for…
IMARAT has made history by becoming Pakistan’s first certified Marriott International operator, a landmark achievement…