ISLAMABAD: The Capital Development Authority (CDA) will soon launch the construction of 10th Avenue in Islamabad, which will be funded under the PSDP by the Federal Government.

invest with imarat

Islamabad’s emerging city centre

Learn More

The 7.6 Kilometres long 10th Avenue project plan submitted by the CDA was approved by the Central Development Working Party CDWP.

The project with a PC-1 cost of Rs11078.000 million will be constructed in three phases and is scheduled to be completed in three years.

Under the phase-I, the construction work will be carried out from Kashmir Highway to Service Road (N) I-9/I-10, costing Rs3901.225 million.

The construction work starting from Service Road North I-9/I-10 to IJP Road will be completed in phase-II, worth Rs3451.225 million.

The work on the third phase will start from Kashmir Highway extending to Khayaban-e-Iqbal, costing Rs3725 .550 million.

The residents of I-10, H-10, I-9, H-9, G-10 and F-10 are to benefit from the construction of the 10th Avenue.

In addition, the capital will witness the ease of traffic congestion on Faqeer Appi Road and 9th Avenue due to the construction of 10th Avenue.

The project will also include the construction of an overhead bridge at Margalla Railway station, establishment of underpasses at G-9/G-10, H-9/H-10, I-9, I-10, F-9, F-10, Jinnah Avenue and Ibn-e-Sina Road, an Interchange at Kashmir Highway and at IJP Road, box culvert/nullah bridge, and the rehabilitation and resettlement of the slums in Sector H-9.

For news and blogs, visit Graana.com.

Maham Tahir

Recent Posts

Pakistan to Gradually End SEZ Tax Exemptions Under IMF-Backed Reforms

Islamabad: The federal government is preparing to gradually withdraw tax exemptions for businesses operating within…

1 day ago

ADB Reviews Karachi Red Line BRT Progress Amid Delays and Utility Challenges

Karachi: A seven-member delegation from the Asian Development Bank (ADB) convened with Sindh’s Minister for…

4 days ago

FBR Considers Tax on High Pensions, Relief for Low-Income Earners in FY2025-26 Budget

Islamabad: The Federal Board of Revenue (FBR) is reviewing two key budget proposals for FY2025-26:…

7 days ago

CDA Proposes Mega Mixed-Use Project ‘Jinnah Square Downtown’ Along Srinagar Highway

The Capital Development Authority (CDA) is progressing with plans for a major mixed-use initiative named…

1 week ago

PDWP Approves PKR 1.99 Billion for Raiwind Road Rehabilitation

The Provincial Development Working Party (PDWP) has sanctioned a major infrastructure project worth PKR 1.99…

1 week ago

WASA to Launch PKR 14 Billion High-Tech Sewerage Project in Lahore Using TBM Technology

The Water and Sanitation Agency (WASA) Lahore is set to initiate a landmark sewerage upgrade…

2 weeks ago